1.Tools and Materials
![]() |
|
![]() |
| (1)Foamed Ceramic Panel |
(2)Anchoring parts |
(3)primer/sealer enhances bonding between the base wall and mortar(for ceramic tile walls only) |
![]() |
![]() |
![]() |
| (4)Cement Mortar provide bonding between foamed ceramic boards and base wall |
(5)Electric drill and drill bits Used to drill in screws for anchoring parts |
(6)Foam Strips for joint filling between foamed ceramic panels |
![]() |
![]() |
|
| (7)Sealant for joint filling between foamed ceramic panels |
(8)Masking Paper protects board edges and surfaces during installation |
⚠️ Tip: All core materials—anchoring parts, foam strips, sealant, mortar and others—can be supplied as a complete kit by our company, simplifying your installation process.
2. Installation Process
(1)Installation on New Walls
![]() |
→ | ![]() |
→ | ![]() |
| Step1:Drill the anchoring parts (1)Mark the drilling positions on the wall according to board size (2)Drill into the wall to install our supplied anchoring parts |
Step2:Apply mortar (1)Spread our cement mortar evenly on the wall surface and the back of the board (2)Ensure proper thickness for full adhesion |
Step3:Insert boards into anchoring parts and attach to wall (1)Place the board into the pre-installed anchoring parts (2)Check that the board is level and flush |
||
| ↓ | ||||
![]() |
← | ![]() |
← | ![]() |
| Step6:Fill joints with foam strips (1)Insert our foam strips into the gaps between boards (2)Apply masking paper along the edges to prevent mortar or sealant contamination |
Step5:Repeat steps 2–4 Continue with the next boards, maintaining vertical alignment and flatness |
Step4:Install top anchoring parts Drill and secure the top part of the board for stability |
||
| ↓ | ||||
![]() |
→ | ![]() |
||
| Step7:Apply sealant (1)Fill the joints with our high-quality sealant (2)Ensure joints are sealed and watertight |
Step7:Apply sealant (1)Fill the joints with our high-quality sealant (2)Ensure joints are sealed and watertight |
(2)Installation on Tiled Walls
- Check tile adhesion:
- Loose tiles → Remove tiles and build a new cement wall
- Stable tiles → Apply a primer/sealer
- Follow the new wall installation process
(3)Installation on Coated Walls
- Build a new cement wall first
- Follow the new wall installation process with our complete set of materials
3. Tips for a Successful Installation
- Ensure each board is level and vertical before fixing
- Clean excess mortar and sealant immediately during installation
- Foam strips should match joint sizes for effective sealing
- Avoid over-applying sealant to maintain a neat finish
- Using our supplied kit (anchoring parts, mortar, foam strips, sealant and others) simplifies installation and ensures high-quality results
Contact Details
Myreal Energy Saving (Shanghai) Co., Ltd.
Contact Person: Mrs. Betsy Ouyang
Tel: +86 177 4080 0950